MS Project Vs Primavera P6
The Following is the difference between the MS Project and Primavera P6.
- Primavera, supports unlimited baselines. And MS-Project supports 11 baselines.
- Primavera allows multiple users to work on a single project and the specific features to be used. AND MS Project doesn’t allow multiple users to work on a single project.
- Primavera allows adding different project expenses like training cost, traveling cost, etc. in addition to the project expenses. MS-Project does not allow the calculation of other expenses.
- Primavera supports up to 200 columns including custom columns, each column giving useful information. MS-Project on the contrary part supports up to 40 columns only.
- Primavera allows the creation of WBS (Work Breakdown Structure) in which activities can be added. In MS-Project activities are made to appear or function like WBS.
- Primavera supports a larger number of activities. MS-Project supports a Less number of activities when compared to Primavera.
- Primavera supports shuffling of onscreen activities using sorting, grouping, etc. MS-project lacks on-screen activity shuffling.
- Primavera is a database-based project management software. MS-Project is file-based project management software.
- Primavera supports a feature known as Progress spotlight to highlight table rows in a particular color. MS-Project does not support any such direct feature instead allows you to create filters for the same.
- Primavera allows creating sub-activities of activity by breaking the main activity into different steps with its own start and finish date. AND MS-Project does not provide any such functionality for creating sub-activities.
- Primavera plan, documents, and other information can be converted to HTML directly from the software. MS Project doesn’t have such an option.
- The Primavera P6 software can create a comprehensive website comprising of complete project details including activities, resources, reports, risks, issues, WBS, and everything that has been entered into the software. This website is a very valuable feature and is not present in MS Project
- Primavera allows you to create a blank custom field. However, it does not set formulas to the fields. Thus, users have to set the formulas manually in each field for each column. AND MS-Project allows creating custom fields with complex formulas and additional values to the field which reduces the manual effort of the user.
- Primavera supports multiple activities relationship in which more than one type of relationship can be created between the activities. AND MS-Project software does not support multiple activity relationships. It allows establishing only one type of relationship between activities.
- Primavera software supports multiple project creation, tracking, and viewing. It allows tracking, multiple projects or Work Breakdown Structure comparisons, cost, and units calculations. AND MS-Project allows multiple projects creation but it does not allow other functions on the multiple projects like tracking multiple projects, cost, other calculations, and comparisons simultaneously.